Before going ahead and transplanting a system into the V2100, there are a few
things to do. First, the instructions recommend putting the rubber covers
on the feet.
I started off by installing the Ultra X-Connect 500W into the bottom area.
You can unscrew the panel and install your PSU if that is easier for you.


Next up is to prepare the motherboard tray with some stand offs.
Lian Li provides a nice small tool to get them installed.

After figuring out the alignment, I installed my Epox 4PCA3+.

Next up is to get my hard drives installed. The drives are to be
installed at the bottom racks in the case. It just requires installing a few
screws on your drive and then sliding them into the rails.


The optical drives are not installed in the same fashion as the
hard drives. They require the the age old skill of tightening a few screws to
get them into place.